Methodology

Engineering methodology & sources

The formulas, energy factors, cost curves and public sources behind the calculators and benchmark datasets on this site.

Scope and accuracy

Every calculator output on this site is a preliminary, AACE Class 5 order-of-magnitude estimate (typical accuracy −20% to −50% low, +30% to +100% high). It is meant to rank options and size a budget conversation. It is not a design, a quote or a performance guarantee, and it must be validated with an ion chromatography report, saturation modeling and treatability testing.

Mass balance

Q_feed [m³/d] = GPM × 5.45097 M_solids [kg/d] = Q_feed × TDS_feed [mg/L] / 1000 Stage concentrate: Q_out = Q_in × TDS_in / TDS_out (full salt rejection) Water recovered by stage = Q_in − Q_out Overall recovery [%] = Σ water recovered / Q_feed × 100

Stage ceilings: RO 70,000 mg/L; OARO 135,000 mg/L; MVR 245,000 mg/L; crystallizer to a cake of 90% solids by weight. In hybrid mode RO is used when feed TDS is below 70,000 mg/L and OARO when it is below 100,000 mg/L for thermal endpoints (below 135,000 mg/L for the membrane endpoint). Crystallizer evaporation uses an approximate brine density of 1,000 + 0.7 × TDS/1000 kg/m³ and leaves cake moisture of one-ninth of the solids mass.

Specific energy by stage

StageSEC usedBasisPublished range
RO3.8 kWh/m³per m³ permeate2.5–5.0
OARO13.0 kWh/m³per m³ permeate6–20
MVR brine concentrator52 kWh/m³per m³ evaporated40–80+
Crystallizer78 kWh/m³per m³ evaporated60–110+
Conditioning factor+15%high silica / CaSO₄ and FGD profiles–

CAPEX curve (mass balance modeler)

CAPEX_mid = 210,000 × GPM^0.72 × f_endpoint × f_mode × f_chemistry f_endpoint: membrane MLD 0.35 · MVR MLD 0.75 · ZLD 1.00 f_mode: direct thermal on feed < 100,000 mg/L 1.25 · otherwise 1.00 f_chem: NaCl 1.00 · high silica 1.10 · lithium 1.15 · FGD 1.20 Range shown: 0.7 × CAPEX_mid to 1.5 × CAPEX_mid

The curve reproduces published installed-cost bands: about $1.8M at 20 GPM, $7.7M at 150 GPM and $30M at 1,000 GPM for full ZLD.

Operating cost

  • Electricity = Σ stage kWh/day × operating days × $/kWh.
  • Pretreatment and antiscalant chemicals per m³ feed: NaCl $0.45, lithium $1.10, high silica $1.40, FGD $1.80.
  • Maintenance and membrane replacement: 3% of mid CAPEX per year for membrane-only trains, 4% when thermal stages are present.
  • Residuals: MLD concentrate × your liquid disposal rate; ZLD cake tonnes × your tipping fee.
  • Levelized operating cost = annual OPEX ÷ annual feed volume.

Hauling vs. evaporator calculator

Annual gallons = gal/week × 52 | gal/month × 12 | m³/month × 264.172 × 12 Utility per gal evaporated: Thermal (gas): 0.0111 MMBtu × $/MMBtu + 0.05 kWh × $/kWh (≈75% thermal efficiency) Vacuum heat pump: 0.70 kWh × $/kWh MVR skid: 0.40 kWh × $/kWh Residual = annual gallons × (1 − reduction) × residual $/gal Maintenance = CAPEX × 6% (thermal) · 5% (vacuum) · 4% (MVR) Auto CAPEX = 3,140 × GPD^0.6 × 1.00 (thermal) · 1.25 (vacuum) · 1.60 (MVR), MVR minimum $150,000

Hauling and residual disposal escalate at the user's rate; utilities and maintenance at 2.5% per year. Cash flows are undiscounted. Tanker loads assume 5,000-gallon vacuum trucks.

Metallurgy screening

Alloy suggestions use the temperature and chloride limits listed in the metallurgy matrix, with stage temperatures assumed at ambient to 45°C for membranes, about 105°C for MVR and about 120°C for crystallizers. Chloride is estimated as 55% of TDS for NaCl-type brines.

Sources

Industry ranges for hauling tiers, ZLD operating cost and technology SEC are compiled from vendor literature, published case studies and technical papers on high-recovery desalination and ZLD, and are reviewed as new data appears.

Send us the stream before you buy the skid.

Share flow, TDS and a lab ion report. We return a preliminary mass balance, a train recommendation and the questions a vendor bid has to answer.