What 40 CFR Part 423 requires

EPA's Steam Electric Power Generating effluent guidelines (40 CFR Part 423) govern wastewater from coal-fired units. The final rule published in May 2024 set zero-discharge limitations for flue gas desulfurization (FGD) wastewater and bottom ash transport water, and numeric mercury and arsenic limits for combustion residual leachate. Zero discharge in practice means recycle, evaporate, or encapsulate the purge so nothing reaches surface water.

Deadlines after the 2025–2026 extension rulemaking

EPA's subsequent deadline-extension rulemaking moved the latest compliance date for the zero-discharge requirements from December 31, 2029 to December 31, 2034, with the date for each plant set in its NPDES permit. Plants that commit to permanently cease coal combustion can use the cessation subcategory through a Notice of Planned Participation (NOPP); indirect dischargers to POTWs have their own pretreatment timelines. Check the current Federal Register text and your permit writer's schedule before locking a project date.

Five to eight years sounds long for a ZLD project. Treatability testing, piloting, permit modification, procurement of titanium equipment and commissioning routinely take four to six years. Plants starting now are not early.

FGD wastewater chemistry

ConstituentTypical FGD purge rangeDesign consequence
Chloride5,000–40,000 mg/LPurge rate set by chloride limit in absorber; drives Ti / C-276 metallurgy
Calcium, magnesiumSaturated with gypsum; Mg often thousands of mg/LSoftening sludge, CaSO₄ scaling, MgCl₂ hygroscopic cake
SeleniumTens to thousands of µg/LSelenate is hard to remove; drove the original 2015 limits
Mercury, arsenicµg/L levelsSolid cake leach behavior, landfill classification
Nitrate, boron, TSSVariable with coal and scrubberBiological and membrane pretreatment loads

Compliance pathways

  1. Recycle and reduce: raise absorber chloride limits, reuse purge in ash conditioning or as makeup, cut purge volume before treatment.
  2. Membrane pre-concentration: softening plus high-recovery RO or OARO to cut the thermal load, where scaling allows.
  3. Thermal ZLD: brine concentrator plus crystallizer, or spray dryer evaporation into the flue gas path.
  4. Encapsulation: mixing concentrated brine with fly ash and lime into a stabilized solid for the landfill, subject to leach testing.

Metallurgy requirements

FGD brines combine high chloride, low pH excursions and evaporative dry-out. Titanium Grade 2 is the usual tube material for brine concentrators; crystallizers and high-temperature zones commonly move to titanium Grade 7 or Hastelloy C-276, which is immune to chloride stress corrosion cracking above 190°C. 316L has no place in hot FGD brine service. See the Cl-SCC matrix.

Salt cake handling and landfill

Mixed chloride cakes with magnesium and calcium chloride are hygroscopic and can re-liquefy in storage. Plan covered storage, leach testing (TCLP) for mercury, arsenic and selenium, and a landfill route: non-hazardous tipping fees run $47.50–$72/ton nationally, hazardous salt cake $250–$600+/ton. The modeler pre-set for FGD purge applies the higher tipping fee automatically.