Aerial view of lined brine evaporation ponds
Benchmark data

Brine disposal tariffs & utility benchmarks

Surface outfall, brine line, UIC deep well, evaporation pond, tanker hauling and on-site ZLD costs, Class 5 CAPEX bands, US industrial electricity and gas, and landfill tipping fees in one sourced table.

  • 27benchmark rows
  • $0.05–$10+/gal hauling
  • $22–$600+/ton landfill

Dataset

Download benchmark dataset (CSV)27 rows · UTF-8 · columns: category, item, low, high, unit, basis_region, source, source_url, note
CategoryItemLow – highUnitBasis / regionSourceNote
Surface dischargeSurface water / ocean outfall0.05 – 0.50USD/m3Global, coastal & permittedUS Bureau of Reclamation, Desalination & Water Purification ResearchEquivalent to about $0.01–$0.08/bbl
Brine lineSAWPA brine line conveyance (piped)0.30USD/m3Southern CaliforniaSanta Ana Watershed Project Authority, Inland Empire Brine Line~$1,141 per million gallons plus capacity units
Brine lineOC San regional treatment pass-through0.46USD/m3Southern CaliforniaOrange County Sanitation District~$1,754+ per million gallons
Brine lineBOD strength surcharge462 – 744USD/1000 lb BODSouthern CaliforniaSanta Ana Watershed Project Authority, Inland Empire Brine LineApplied by pollutant load
Brine lineTSS strength surcharge579 – 855USD/1000 lb TSSSouthern CaliforniaSanta Ana Watershed Project Authority, Inland Empire Brine LineApplied by pollutant load
Brine lineTrucked waste tipping at brine line station4.52USD/m3Southern CaliforniaSanta Ana Watershed Project Authority, Inland Empire Brine Line$0.0171/gal
Deep well injectionUIC Class I/II, piped on-site well0.50 – 3USD/m3United StatesUS EPA Underground Injection Control program (40 CFR 144/146)Permit takes 1–3 years; seismic and MIT requirements
Deep well injectionUIC Class I/II, trucked to commercial well2 – 10USD/m3United StatesUS EPA Underground Injection Control program (40 CFR 144/146)About $0.30–$1.50+/bbl
Evaporation pondsLined evaporation pond (all-in)2 – 10USD/m3Arid inland sitesUS Bureau of Reclamation, Desalination & Water Purification ResearchLand, double HDPE liner, net evaporation dependent
Tanker haulingNon-hazardous general brine0.05 – 0.30USD/galUnited StatesPublished vendor and industry ranges, compiled by Brine TechnologiesBefore fuel surcharges
Tanker haulingHigh-TDS / POTW-rejected non-hazardous brine0.50 – 1.5USD/galUnited StatesPublished vendor and industry ranges, compiled by Brine TechnologiesSpecial waste acceptance
Tanker haulingRCRA hazardous brine2 – 10USD/galUnited StatesUS EPA Resource Conservation and Recovery Act programManifest and generator liability apply
On-site treatmentOn-site ZLD / crystallization operating cost10 – 45USD/m3Small-to-mid industrialPublished vendor and industry ranges, compiled by Brine TechnologiesEnergy 50–70% of OPEX; $0.03–$0.15/gal
Installed CAPEXSmall industrial evaporator, 100–2,000 GPD50,000 – 500,000USDClass 5 order of magnitudeAACE International Recommended Practice 18R-97 (cost estimate classification)Packaged skid
Installed CAPEXSmall-to-mid ZLD package, 1–20 GPM250,000 – 2,000,000USDClass 5 order of magnitudeAACE International Recommended Practice 18R-97 (cost estimate classification)Membrane + thermal
Installed CAPEXMid-to-large industrial ZLD, 50–300 GPM5,000,000 – 25,000,000USDClass 5 order of magnitudeAACE International Recommended Practice 18R-97 (cost estimate classification)Field-erected
Installed CAPEXUtility / mega-scale ZLD, 1,000–3,000+ GPM25,000,000 – 50,000,000USDClass 5 order of magnitudeAACE International Recommended Practice 18R-97 (cost estimate classification)High end open-ended
Utility tariffUS industrial electricity, 2025 average0.085 – 0.0862USD/kWhUnited StatesUS EIA Electric Power Monthly8.50–8.62 ¢/kWh
Utility tariffUS industrial electricity, 2026 preliminary0.0891 – 0.0909USD/kWhUnited StatesUS EIA Electric Power Monthly8.91–9.09 ¢/kWh
Utility tariffHenry Hub natural gas, 20253.53USD/MMBtuUnited StatesUS EIA Short-Term Energy OutlookSpot benchmark
Utility tariffHenry Hub natural gas, 2026 forecast3.37USD/MMBtuUnited StatesUS EIA Short-Term Energy OutlookSTEO forecast
Utility tariffIndustrial delivered natural gas4.5 – 8.5USD/MMBtuUnited StatesUS EIA Short-Term Energy OutlookDepends on basis and contract
LandfillMSW / non-hazardous tipping fee, national average63 – 72USD/tonUnited StatesEnvironmental Research & Education Foundation (EREF), MSW tipping fee analysis
LandfillMSW / non-hazardous tipping fee, state median47.5 – 55USD/tonUnited StatesEnvironmental Research & Education Foundation (EREF), MSW tipping fee analysis
LandfillMSW tipping fee, South Central region22 – 32USD/tonUS South CentralEnvironmental Research & Education Foundation (EREF), MSW tipping fee analysisLowest region
LandfillMSW tipping fee, Northeast region95 – 120USD/tonUS NortheastEnvironmental Research & Education Foundation (EREF), MSW tipping fee analysisHighest region
LandfillRCRA hazardous salt cake landfilling250 – 600USD/tonUnited StatesUS EPA Resource Conservation and Recovery Act programUpper end open-ended

How to read the ranges

Each row is a published or widely quoted range, not a quote for your site. Disposal prices move with distance, waste acceptance criteria, fuel surcharges and contract volume; brine line charges also depend on purchased capacity. Use the low end for screening only when your stream is clean, close and steady.

Unit conversions used

  • 1 m³ = 264.172 US gal = 6.2898 bbl
  • 1 million gallons (MG) = 3,785.41 m³
  • 1 GPM = 5.45097 m³/day
  • 1 metric tonne = 1.10231 short tons

Where these numbers are used

The MLD/ZLD modeler uses the electricity, disposal and landfill rows as defaults. The hauling ROI calculator uses the tanker hauling tiers for its stream presets. Formulas and assumptions are on the methodology page.

Citing this dataset

Brine Technologies (2026). Brine Disposal Tariffs & Utility Benchmarks. https://brinetechnologies.com/benchmarks/disposal-tariffs/